Amended
# 288

Bridge Repair

By December 2024, Public Works will advance five of the 13 bridges currently programmed to the next phase of authorization.

Key Steps

1 2 3 4
Secure required funding programming in the FTIP through Caltrans. Continue working with Caltrans to obtain approval of documents to complete current phases. Submit authorization paperwork to Caltrans for approval to proceed to next phase.  
Plan Reference:
Target:
Baseline: Progress:
3.A.ii, 3.B.ii, 3.C.ii 5 Bridges Moved to Next Project Phase 0 40%(2)